Dear Neighbour,
Welcome to the latest issue of our Neighbourhood Update for St Finian’s, Mullingar. JJ Rhatigan/ABM Joint venture have been appointed to deliver Project Nore which is a bundle of 7 schools located between Kilkenny, Tipperary, Kildare and Mullingar.
JJ Rhatigan has been appointed for the upgrading and refurbishment of the main school building (which is a protected structure). The development consists of the construction of a two-storey western extension (West Block) to the main school building; a new two-storey block to the north (North Block) to accommodate technology classrooms and science laboratories, which will be connected to the existing main building via a first-floor enclosed corridor bridge; a new three-storey block (East Block) to the east of the main building to accommodate the art classrooms, which will be connected to the existing main building via a four-storey enclosed stairway; a new changing block attached to the existing sports block; a new detached single-storey substation and maintenance store block to the west of the main building; and all associated demolition works.
Works to the school grounds will consist of the construction of a new all-weather pitch to the north and 6 No. ball courts to the west, landscaped terraced seating to the rear of the existing building, and associated soft and hard landscaping throughout. The development also consists of a new vehicular access from the old Longford Road, which will facilitate a new internal bus drop-off and pick-up area. The development will be carried out over a three-year period, with works broken into two phases.
Phase 1 consists of associated demolition works and the construction of the new North and East Blocks and new Changing Block; refurbishment of the existing sports hall and church; and construction of the new all-weather pitch, ball courts, new vehicular access, and all associated landscaping works to Phase 1.
Phase 2 consists of the refurbishment of the main building and construction of the new West Block, and all associated landscaping works.
The school will remain active throughout the construction period.
St. Mary’s Special School, which is located within St. Finian’s, will be delivered by ABM, and a separate newsletter will be issued.
UPDATE – August 2026
The roof tent on the West Block has been fully removed, with the new slating and guttering now completed. Works on the central roof area will remain under the temporary roof tent until slating is practically completed. The external lime plaster, including the decorative moulds, is nearing completion on the East Block elevation adjacent to the Chapel. External lime plastering to the West Block has commenced, and decorative moulds are also progressing in this zone. Lime plastering to the courtyards on the East and West is ongoing. Internal partitions are progressing well on all floors. The new sash windows are also continuing to be installed on the lower floors. Internal doors and screens are being installed on the upper floors. Preparation works to receive floor finishes and fitted furniture are underway. Electrical and mechanical services are being installed in X1 on all floors.
X2 Mechanical and electrical services are ongoing on both the lower ground floor and ground floor. Ceilings are also progressing on both floors.
Works to the main campus road are ongoing, including new kerbing, drainage, and footpaths.
Looking ahead to August, we will be working on the main St. Finian’s campus road improvements. We will also continue with the central roof slating, rooflight, and lead walling, and the central roof tent will be removed. We will continue external lime plastering on the East and West Blocks, and the continuation of sash window installation throughout. Internally, doors, screens, flooring, and painting will continue. M&E works will continue throughout both the X1 and X2 buildings, with ceiling installation following in most zones.
Together, these milestones show steady progress towards delivering state-of-the-art facilities that will benefit the St. Finian’s community for generations to come.
School Liaison: Working together alongside the school, a comprehensive separation has been implemented between construction works and school areas. The safety and continuity of the school is our main priority, and this separation will remain in place until the completion of the project to ensure no disruption to everyday school life.
CONSTRUCTION WORK HOURS & PARKING
Monday to Friday: as per planning.
Saturday: as per planning.
Provision for parking has been made within our compound for our construction workers and for all construction-related traffic. Site access will be from the old Longford Road.
HEALTH, SAFETY & ENVIRONMENT
As the Main Contractor, the health and safety of our workers and the public is a top priority for JJ Rhatigan/ABM. We have drafted a traffic management plan that will be implemented for the duration of the construction works to minimise the impact on the public and local residents. The site will be fully secured for the duration of the works, and the vast majority of the works will be carried out within the confines of this area. It is important that children understand that construction sites are not a safe place to play and that they should not try to enter construction sites at any time. We would appreciate parents’ assistance in getting this point across to young children.
Construction sites are defined as high-risk work areas, with those who work on site having specialised training and equipment to undertake their tasks. Once established on site, JJ Rhatigan/ABM will be completing school visits and community initiatives to outline this.

JJ Rhatigan & Company is proud to support and cooperate with the Considerate Constructors Scheme to commit to care regarding the appearance of our site, respect the community in which we work, protect the environment by our methods of working and choice of design and materials, secure everyone’s safety and value our workforce. We strive to maintain the highest standards on all our projects.
UPCOMING WORKS
JJ Rhatigan/ABM will be providing regular Neighbourhood Updates to give our neighbours information on the works to be carried out.
We now have a website set up to provide these updates: www.rhatiganabm.com. All future updates will be provided via the website.
We apologise in advance for any inconvenience the construction activities may cause, and we thank you for your patience and consideration. Please be advised that it is our policy to ensure that all efforts are made to minimise disruption to the neighbourhood for the duration of the construction period.
PROJECT QUERIES
Should you require any further information please do not hesitate to contact us via the website.