Dear Neighbour,
Welcome to the latest issue of our Neighbourhood Update for St Marys Special School Mullingar. JJ Rhatigan/ABM have been appointed to deliver St Marys Mullingar.
The project will consist of A new build single storey school with associated parking and play areas. New external works around the school to include landscape car parks, new entrance off the Old Longford Road, boundary screening, grass areas, play space, bike parking, paths, gardens, bin stores, tool shed.
Update – April 2024.
Since our last newsletter substructure and site works have been progressing progressed as planned.
We have installed 65% of the precast frame and are on target to have the concrete structure completed by the end of May. Window installation and External blockwork have commenced with Foul Pumping chamber and all foul drainage completed.
Site Hours, Parking and Access.
Site hours shall be in line with the granted planning conditions, these being;
- Monday to Friday – as per planning
- Saturday 8am – as per planning.
Provision for parking has been made within our compound for the construction workers and for all construction related traffic. The site access will be from the old Longford Road
Health, Safety and Environmental.
Health and Safety of our workers and the public is a top priority for Rhatigan ABM Ltd. We have drafted a traffic management plan that will be implemented for the duration of the construction works to minimise the impact on the public and residents. The site will be fully secured for the duration of the works and most of the works will be carried out within the confines of this area.
It is important that children understand that construction sites are not a safe place to play, and they should not try to enter construction sites at any time. We would appreciate parents’ assistance in getting this point across to young children.
Construction sites are defined as high-risk work areas with those who work on site having specialised training and equipment to undertake their tasks. Once established on site JJ Rhatigan/ABM will be completing school visits / community initiatives to outline this.

Upcoming Works.
Upcoming works include commencing Roof membrane installation, External leaf blockwork and insulation, Mechanical and Electrical are due to commence by the end of April. The construction of the Tool shed, boundary walls, watermain and services ducting starting in early May.
Project Queries.
Should you require any further information please do not hesitate to contact us here