Dear Neighbour,
Welcome to the April 2024 issue of our Neighbourhood Update for CBS Secondary School, Kilkenny. Please take a moment to read this notice about the upcoming works in your locality.
Works since last neighbourhood update
Works include:
• Raft Foundations Complete
• Boundary Retaining Wall Construction Ongoing
• CBS School Playing Field Formation including Topsoil Ongoing
• Precast Superstructure (School) Ongoing
• External Windows/Doors and Curtain Walling Commenced (School)
• Internal M+E 1st fix commenced (Commenced)
• Outer Leaf Blockwork commenced.
• ESB Substation (School) Ongoing
• CBS Access Road Formation Ongoing.
• Utility Ducting Installation Ongoing (School and Access Road)
• Deep Drainage Runs including Sewer, Storm and Rainwater Harvesting ongoing.
• Rainwater Harvesting Tank and Sewer Pumping Station installed.
• Kerbing and Footpaths (Access Road) Ongoing
• ESB/EIR Diversions Complete @ Dunningstown Road.
• Planning works ahead of commencing upgrading works at Dunningstown Road and Talbots Gate/Freshford Road.
All the necessary Health and Safety systems and traffic management will be put in place to ensure your safety at all times during these works.
CONSTRUCTION WORK HOURS & PARKING
Monday to Friday – as per planning. Saturday – as per planning.
Provision for parking has been made within our compound (lands off Dunningstown Road South adjacent to the new school) for our construction workers and for all construction related traffic.
HEALTH, SAFETY & ENVIRONMENT
As the Main Contractor the health and safety of our workers and the public is a top priority for JJ Rhatigan/ABM.
It is important that children/teenagers understand that construction sites are not a safe place to play, and they should not try to enter construction sites at any time and/or MUST NOT ENTER SITE AT ANY TIME. We would appreciate parents’ assistance in getting this point across to young children.
Construction sites are defined as high-risk work areas with those who work on site having specialised training and equipment to undertake their tasks.
JJ Rhatigan & Company is proud to support and cooperate with the Considerate Constructors Scheme to commit to care regarding the appearance of our site, respect the community in which we work, protect the environment by our methods of working and choice of design and materials, secure everyone’s safety and value our workforce. We strive to maintain the highest standards on all our projects.
UPCOMING WORKS
Including:
• Commencing Road Upgrade including services along Dunningstown Road including Storm, Ducting, Watermain installation and Road widening.
• Commencing site works (prior to Road Upgrade) via Talbots Gate.
We apologies in advance for any inconvenience the construction activities may cause and to thank you for your patience and consideration. Please be advised that it is our policy to ensure that all efforts be made to ensure minimal disruption to the neighbourhood for the duration of the construction period.
PROJECT QUERIES
Should you require any further information please do not hesitate to contact us here.