Welcome to the latest issue of our Neighbourhood Update for St Finian’s, Mullingar. JJ Rhatigan/ABM Joint venture have been appointed to deliver Project Nore which is a bundle of 7 schools located between Kilkenny, Tipperary, Kildare and Mullingar.

JJ  Rhatigan have been appointed for the upgrading and refurbishment of the main school building (which is a protected structure).The construction of a two-storey western extension (West Block) to the main school building, a new two-storey block to the north (North Block) to accommodate technology classrooms and science laboratories which will be connected to the existing main building via a first-floor enclosed corridor bridge, a new three-storey block (East Block) to the east of the main building to accommodate the art classrooms, which will be connected to the existing main building via a four-storey enclosed stairway, a new changing block attached to the existing sports block, new detached single-storey substation and Maintenance store block to the west of the main all associated demolition works,  Works to the school grounds will consist of the construction of a new all-weather pitch to the north, 6no Ballcourts to the west , Landscaping terraced seating to the rear of the existing building and associated soft and hard landscaping throughout, The Development also consists of a new vehicular access from the old Longford road which will facilitate a new internal bus drop off and pick up area

The development will be over a 3-year period with works broken into 2 phases.

Phase 1 – consists of associated demolition works and construction of new North and East blocks, New Changing block, refurbishment of existing sports hall and church and construction of new all-weather pitch, Ballcourts, new vehicle access and all associated landscaping works to phase 1.

Phase 2 – consists of the refurbishment of the main building and construction of new west block and all associated landscaping works,

The school will remain active throughout the construction duration.

St Mary Special School which is located within St Finian’s will be delivered by ABM and separate newsletter will be issued. 

UPDATE – December 2024

We have achieved a major milestone with all our buildings now weathertight. All temporary roof covering has been removed. This is important as we enter the winter months and allows us progress internally without weather issues.

The school has also taken ownership of the new sheds and Bin stores, which completes all our works around the carpark section.

Our plan for December is to progress the five buildings and associated works externally. This includes Mechanical and Electrical 1st and 2 fix works. Internal joinery, flooring, fitted furniture and ceiling installs.

Both the X3 and X6 building are progressing with the finishes including fitting out the various Science labs and Art Rooms and technology rooms. We have removed the external scaffold to the X6 building and its finished façade is now visible.

We are in progress of working on the Old Longford road to including the raised pedestrian crossing and associated signage.

North Block

Internal fitout and external works on going.

East Block & Gym

Roof works and strike the external Scaffold coming down.

Sports Hall

Temporary Roof removed and external scaffold coming down, internal fit out commencing in Mid-December.

Church Works

Internal M&E works ongoing, including painting of the Church and remedials to external windows.

Boundary Fencing along

The new timber fence along the College Hill housing estate will commence in January 2025.

CONSTRUCTION WORK HOURS & PARKING

Monday to Friday – as per planning.
Saturday – as per planning.

Provision for parking has been made within our compound for our construction workers and for all construction related traffic. The site access will be from the old Longford Road

HEALTH, SAFETY & ENVIRONMENT

As the Main Contractor the health and safety of our workers and the public is a top priority for JJ Rhatigan/ABM. We have drafted a traffic management plan that will be implemented for the duration of the construction works to minimise the impact on the public and local residents. The site will be fully secured for the duration of the works and the vast majority of the works will be carried out within the confines of this area. It is important that children understand that construction sites are not a safe place to play, and they should not try to enter construction sites at any time. We would appreciate parents’ assistance in getting this point across to young children.

Construction sites are defined as high-risk work areas with those who work on site having specialised training and equipment to undertake their tasks. Once established on site JJ Rhatigan/ABM will be completing school visits / community initiatives to outline this.

UPCOMING WORKS

JJ Rhatigan/ABM will be providing regular Neighbourhood Update to give our neighbours information on the works to be carried out.

All future updates will be provided via this website.

We apologies in advance for any inconvenience the construction activities may cause and also to thank you for your patience and consideration. Please be advised that it is our policy to ensure that all efforts be made to ensure minimal disruption to the neighbourhood for the duration of the construction period.