CBS Secondary School, Kilkenny – January 2025 update

Dear Neighbour,
Welcome to our January 2025 issue of our Neighbourhood Update for CBS Secondary School, Kilkenny. Please take a moment to read this notice about the upcoming works in your locality.

Works since last neighbourhood update

Works include:
Section 7A (School and associated site works)
Ongoing internal fitout
Ongoing externals including external school envelope and school roof finishes.
External Site works ongoing including Kerbing, Paving, Footpaths and Topsoiling including School Field.
ESB Substation Completed
Boundary Treatments commenced (Fencing)
School Utility Connections have started (Water, Power and Gas)

Section 7B (including East Dunningstown)
CBS Access Road Tarmac Basecourse and Binder ongoing (no access to Public)
Accommodation Works to Private Entrances along Dunningstown Road ongoing
Both lanes opened on Dunninsgtown Road to public.
Permanent Traffic Light Installation 1st Fix completed.

Section 7C (including West Dunningstown)
Both lanes opened on Dunninsgtown Road to public.
Accommodation Works to Private Entrances along Dunningstown Road ongoing

Section 7D (including Talbots Gate/Court and Freshford Road Junction)
Kerbing and footpaths ongoing
Installation of below Ground services ongoing.
Tarmac Base and Binder completed in Talbots.
Freshford Roadworks have commenced and no access to Talbots from Freshford Road (and vice versa) as per attached TMP
Talbots Court and Talbots Gate Residents to enter Dunningstown Road allowing Road works on Freshford Road as per attached TMP.


All the necessary Health and Safety systems and traffic
management will be put in place to always ensure your safety during these works.

CONSTRUCTION WORK HOURS & PARKING
Monday to Friday – as per planning.
Saturday – as per planning.
Provision for parking has been made within our compound (Lands off Dunningstown Road South adjacent to the new
school) for our construction workers and for all construction related traffic.

HEALTH, SAFETY & ENVIRONMENT
As the Main Contractor the health and safety of our workers and the public is a top priority for JJ Rhatigan/ABM.

It is important that children/teenagers understand that construction sites are not a safe place to play, and they
should not try to enter construction sites at any time and/or MUST NOT ENTER SITE AT ANY TIME. We would appreciate parents’ assistance in getting this point across to young children.

Construction sites are defined as high-risk work areas with those who work on site having specialised training and
equipment to undertake their tasks.

JJ Rhatigan & Company is proud to support and cooperate with the Considerate Constructors Scheme to commit to
care regarding the appearance of our site, respect the community in which we work, protect the environment by our methods of working and choice of design and materials, secure everyone’s safety and value our workforce. We strive to maintain the highest standards on all our projects.

UPCOMING WORKS
Section 7B and 7C
Handover of Dunningstown Road to KCC (No access to CBS Access Road Remains)

Section 7D (including Talbots Gate/Court and Freshford Road Junction)
Handover of part Talbots Road to KCC
Freshford Road Works ongoing
Work on the link road to the Freshford road and Freshford Road Roundabout is expected to be completed by April 2025.

We apologies in advance for any inconvenience the construction activities may cause and to thank you for your
patience and consideration. Please be advised that it is our policy to ensure that all efforts be made to ensure minimal disruption to the neighbourhood for the duration of the construction period.

Project Phases

Aerial Progress Photograph of School (Section 7A)

Aerial Progress Photograph of School (Section 7A)

Current Traffic Management Plan

Project Queries Should you require any further information please do not hesitate to contact us here