St. Finian’s Secondary School, Mullingar – December 2025 Update

Dear Neighbour,

Welcome to the latest issue of our Neighbourhood Update for St Finian’s, Mullingar. JJ Rhatigan/ABM Joint venture have been appointed to deliver Project Nore which is a bundle of 7 schools located between Kilkenny, Tipperary, Kildare and Mullingar.

JJ  Rhatigan have been appointed for the upgrading and refurbishment of the main school building (which is a protected structure).The construction of a two-storey western extension (West Block) to the main school building, a new two-storey block to the north (North Block) to accommodate technology classrooms and science laboratories which will be connected to the existing main building via a first-floor enclosed corridor bridge, a new three-storey block (East Block) to the east of the main building to accommodate the art classrooms, which will be connected to the existing main building via a four-storey enclosed stairway, a new changing block attached to the existing sports block, new detached single-storey substation and Maintenance store block to the west of the main all associated demolition works,  Works to the school grounds will consist of the construction of a new all-weather pitch to the north, 6 no Ballcourts to the west , Landscaping terraced seating to the rear of the existing building and associated soft and hard landscaping throughout, The Development also consists of a new vehicular access from the old Longford road which will facilitate a new internal bus drop off and pick up area

The development will be over a 3-year period with works broken into 2 phases.

Phase 1 – consists of associated demolition works and construction of new North and East blocks, New Changing block, refurbishment of existing sports hall and church and construction of new all-weather pitch, Ballcourts, new vehicle access and all associated landscaping works to phase 1.

Phase 2 – consists of the refurbishment of the main building and construction of new west block and all associated landscaping works,

The school will remain active throughout the construction duration.

St Mary Special School which is located within St Finian’s will be delivered by ABM and separate newsletter will be issued. 

UPDATE – December 2025

After completing their first four months in the new school building, the pupils and staff of St. Finian’s College are now looking forward to the Christmas holidays. They have enjoyed the past term, and the new facilities have been a pleasure to teach and learn in. Meanwhile, work on phase two of the redevelopment of the existing building continues.

The slates on the roof of the East wing of X1 have now been completely stripped and removed, repair works has begun on the timber rafters, insulation has been replaced between joists and  battening has begun – all works being completed below the protective roof tent.  External render is being removed on the West wing and rear courtyard and will soon be completed. Scaffolding to the West wing and X2 building are nearing completion.

Internal demolition works and removal of flooring have continued on all floors. Mechanical and electrical containment works are ongoing in the Attics and this has also commenced in the floors and in vertical risers. Internal plaster scud and finishing out coats are ongoing.  

The X2 building roofing works have just commenced. Windows and doors installation to this new extension are ongoing. All opes from the X1 to X2 building have now been broken through. External blockworks to the X2 building has also commenced.

Looking ahead to the new year the project will be focused on works to the X2 building’s roof, external façade and making it weathertight along with the commencement of M&E installation, containments etc… X1 works will focus on the slating the roof of the East block, the external Lime render plaster on X1 one will be continued also weather depending in the new year. Internally, fire proofing works n the floors including M&E containment will continue along with internal plastering. Demolition works will continue also on the lower floors.

Together, these milestones show the steady progress towards delivering state-of-the-art facilities that will benefit the St. Finian’s community for generations to come.

School Liaison: working together alongside the school a comprehensive separation has implemented between construction works and school areas, the safety and continuity of school is our main priority this will remain here till the completion of the project to ensure no disruption to everyday school activities.

Construction Work Hours & Parking

Monday to Friday – as per planning.
Saturday – as per planning.

Provision for parking has been made within our compound for our construction workers and for all construction related traffic. The site access will be from the old Longford Road

Health, Safety & Environment

As the Main Contractor the health and safety of our workers and the public is a top priority for JJ Rhatigan/ABM. We have drafted a traffic management plan that will be implemented for the duration of the construction works to minimise the impact on the public and local residents. The site will be fully secured for the duration of the works and the vast majority of the works will be carried out within the confines of this area. It is important that children understand that construction sites are not a safe place to play, and they should not try to enter construction sites at any time. We would appreciate parents’ assistance in getting this point across to young children.

Construction sites are defined as high-risk work areas with those who work on site having specialised training and equipment to undertake their tasks. Once established on site JJ Rhatigan/ABM will be completing school visits / community initiatives to outline this.

JJ Rhatigan & Company is proud to support and cooperate with the Considerate Constructors Scheme to commit to care regarding the appearance of our site, respect the community in which we work, protect the environment by our methods of working and choice of design and materials, secure everyone’s safety and value our workforce. We strive to maintain the highest standards on all our projects.

Upcoming Works

JJ Rhatigan/ABM will be providing regular Neighbourhood Update to give our neighbours information on the works to be carried out.

We now have a website set up to provide these updates.

www.rhatiganabm.com

All future updates will be provided via the website.

We apologies in advance for any inconvenience the construction activities may cause and also to thank you for your patience and consideration. Please be advised that it is our policy to ensure that all efforts be made to ensure minimal disruption to the neighbourhood for the duration of the construction period.

Project Queries

Should you require any further information please do not hesitate to contact us via the website.